Thursday, August 30, 2007

Were done until next Tuesday. Stairs reassembled, lid with the scaffolding out of the way. Dave calking the siding to trim and the first coat of mud.


Wednesday, August 29, 2007

Siding and trim done, drywall patched. Will start mudding and reassemble stairs tomorrow.

Tuesday, August 28, 2007

The door is hung, doggie door and hardware installed. Trim and drywall patching next.


Monday, August 27, 2007

The half hole. Had to wait for the electrician so will set the door tomorrow. Cut a couple of holes in the garage to reroute the power, which is done.


Tuesday, August 21, 2007

We finished setting up this morning and started prep for the fascia, and ran most of the t&g. Will finish tomorrow.


Friday, July 13, 2007

Tree removal


Monday, June 25, 2007

Bruce staining the gates.
The finishing touches to the deck area.


Wednesday, June 20, 2007

The project continues.


Monday, February 26, 2007

More.
The fine details.


Friday, February 09, 2007

For the latest pictures of the siding job click the Lakeforest const. link

Saturday, January 06, 2007


We started the siding on the back wall and worked around both sides to the front where it all came together in the corner between the garage and the house. There are mill differences in the siding material, and variations in the 1" chink joint, our courses were within a 16th of an inch where they came together. We some lucky boys!!

Monday, December 11, 2006

Mel, you have passed final inspection.

Wednesday, December 06, 2006

Thank you Mel.

Tuesday, December 05, 2006

Soffett detail with hidden vent. Or will be when we hang the shingle mold.

Thursday, November 30, 2006

Monday, November 27, 2006

The video below is a software/camera test.

Sunday, November 26, 2006

Building stall doors for Grumpys restrooms.