Tuesday, October 09, 2007
Laying out the foundation again. The surveyors pins are off, still. The hole, and pulling the well pump to hook up the water.
Tuesday, October 02, 2007
The hole is dug. Should start forming the footings Thursday.
Sunday, September 30, 2007
Excavation started.
Thursday, September 27, 2007
Friday, September 21, 2007
Ruff grade
Lot pep.
Tuesday, September 18, 2007
Should start excavation tomorrow.
Friday, September 14, 2007
Prepping and installing posts and picket frames. Will be back to install the pickets Monday or Tuesday. The electrician will be in next week to move the switch and light, then we will finish the drywall patching and texture.
Tuesday, September 11, 2007
Joe at his new job, Manager Wagner Rents. Good for you Joe!
Thursday, August 30, 2007
Were done until next Tuesday. Stairs reassembled, lid with the scaffolding out of the way. Dave calking the siding to trim and the first coat of mud.
Wednesday, August 29, 2007
Siding and trim done, drywall patched. Will start mudding and reassemble stairs tomorrow.
Tuesday, August 28, 2007
The door is hung, doggie door and hardware installed. Trim and drywall patching next.
Monday, August 27, 2007
The half hole. Had to wait for the electrician so will set the door tomorrow. Cut a couple of holes in the garage to reroute the power, which is done.
Tuesday, August 21, 2007
We finished setting up this morning and started prep for the fascia, and ran most of the t&g. Will finish tomorrow.