Same
Project complete.
Doing some fine tuning with the lift.
Ready for floor joist.
Ground floor for a new log home.
Latest project.
Thursday, June 15, 2006
Looking from the other direction.
Close up from the top.
The finished wall sections.
Back filling the hard way.
Installing last courses.
Wednesday, June 14, 2006
We have 2 more courses to run, the power went out in the area right at 12 so we had to stop for the day. I was out there around 3 and it's back on. So it will be done tomorrow morning.
Almost done.
Monday, June 12, 2006
Filled and cut and ready to start the second tier. The cut was done in 2 parts to protect the trees which are within a foot of the cut. And also to protect the lawn.
Back filling the first tier with the cut from the second tier.
Starting the second tier cut.
Saturday, June 10, 2006
same
Completed first level.
Wednesday, June 07, 2006
Day 3. We have had a lot of shovel work. The upper section has to be cut back another 2 1/2 feet once we reach the 3 foot hight of the first level. We are hoping to do this with out disterbing the trees.
Tuesday, June 06, 2006
We had a lot of shovel work to do before we could start laying timbers. Should be up to the first 3 foot step tomorrow.